Spool prefabrication in the new Westfalen power plant

In June 2009 the Kraftanlagen München subsidiary FINOW Rohrsysteme GmbH was awarded the contract for the complete prefabrication of the HP piping systems for the hot reheat and cold reheat sections, as well as for the associated ancillary systems, of the new 2 x 800 MW Westfalen power plant.

 

Special features of this contract include the advanced technical requirements of the power plant and a high degree of prefabrication, which will optimize the on-site installation time. Kraftanlagen München is responsible for planning, supply and installation.



Building Contractor

RWE Power AG


Services

The contract comprises the prefabrication of the following piping systems:

 

Hot reheat:                             600 °C

Main

dimensions:     Ext. diameter 690 x 44

 

Cold reheat:                           360 °C

Main

dimensions:     Ext. diameter 690 x 32

 

Materials:   X10CrWMoVNb9-2 (P92),

                   16Mo3

 


Execution period

August 2009- May 2010